  • 28 Oct 2022 by Metro

    I-5 NCEP Weekly Look-Ahead: October 31 – November 6, 2022 

     

     

    Prepare for weeknight intermittent lane reductions in both directions from SR-14 to Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays and Saturdays as needed.

    SR-14 to Magic Mountain Pkwy
    Weldon Canyon Bridge rebar, concrete, excavation, shoring, and falsework preparation activity. Prepare for work in the center median and along the northbound and southbound I-5 shoulders from 7am to 4pm. | More Information

    Gavin Canyon Undercrossing bridge foundation work, crossing over The Old Road. Prepare for work along the southbound outside shoulder behind k-rail between Calgrove Bl and Weldon Canyon Rd. Activities include auger drilling, setting of steel rebar, and concrete work. Construction access from The Old Road may be utilized. | More Information

    Southbound outside shoulder excavation, shoring and retaining wall work between Calgrove Bl and Weldon Canyon Overcrossing. Prepare for intermittent closures of the southbound Calgrove Bl on-and off-ramps from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. | More Information

    • Southbound on-ramp detours:  
      • Westbound Calgrove Bl: Right on the Old Rd, merge onto San Fernando Rd, right on Sepulveda Bl, merge onto Roxford St, enter southbound I-5 at Sepulveda Bl/Roxford St on-ramp.  
      • Eastbound Calgrove Bl: Enter northbound I-5 Calgrove Bl on-ramp, exit northbound Lyons Av/Pico Canyon Rd off-ramp, right on Lyons Av, enter southbound I-5 at Lyons Av on-ramp. 

    Center median retaining wall construction, paving, and concrete barrier work.  Activities include excavation, shoring, form, and concrete work planned to continue between SR-14 and Valencia Bl. | More Information

    Slope soil stabilization (soil nail installation) along outside shoulders in both directions between Weldon Canyon bridge and Gavin Canyon Undercrossing. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information

    Rebar, form, concrete, and falsework installation work for the Butte Canyon Bridge between Pico Canyon Rd/Lyons Ave and McBean Pkwy. | More Information

    Magic Mountain Pkwy to Parker Rd
    Grading, excavation, and equipment mobilization behind k-rail along southbound I-5 and The Old Road in preparation for sound wall construction between Villa Canyon Rd and Hasley Canyon Rd. | More Information 

    Center median work behind concrete barriers will continue between SR-126 and Parker Rd. Activities include excavation, asphalt removal, drainage pipe installation, placement of base, stockpiling of material, and paving. | More Information    

    Rebar, form, excavation, and utility work in the I-5 center median for the Castaic Creek Bridge between SR-126 and Hasley Canyon Rd. | More Information  

    Upcoming Activity in November
    Falsework installation for construction of Weldon Canyon Rd bridge, requiring multiple weeknight directional closures of I-5 from 10pm to 4am.  

    • I-5 closure limits are between Calgrove Bl and SR-14
    • Primary detour routes include SR-14, Newhall Ranch Rd, and Golden Valley Rd. Local access is available to I-5 ramps between Calgrove Bl and Newhall Ranch Rd. 
      • Specific dates and details are to be provided in future construction notices.  


    Essential Details

    • Work hours: Monday through Friday and Saturday, as needed between 7am-4pm and 7pm-6am. Crews will begin to mobilize at 6am.   
    • No two consecutive ramps in the same direction will not be closed at the same time. Detours to the next on-ramp will be posted for each closure.   
    • Traffic will be maintained in each direction.    
    • All lanes will be reopened by 6am each morning.     
    • No lane closures will be implemented during morning or evening peak traffic hours.   
    • The speed limit in construction work zones is reduced to 55-miles per hour.   

    Noteworthy 
    Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.  

     


    Metro's Community Relations team has created a Frequently Asked Questions (FAQs) document that is now available to you as a resource. |  More Information

    Our project team invites you to join our e-mailing list to get the latest details on upcoming construction. |  More Information

    See all active construction notices for this project.| More Information

     

  • 25 Oct 2022 by SCV Water

    NEWS RELEASE
    DATE: October 25, 2022
    FOR IMMEDIATE RELEASE


    SCV Water Hosts Virtual Bridgeport Community Listening Session on Nov. 2
    Attendees will learn more about a water treatment facility planned along the bike path south of Bridgeport Park


    SANTA CLARITA – SCV Water invites the community to the Virtual Bridgeport Community Listening Session. Attendees will learn more about the planned groundwater treatment facility as well as hear updates from the August Community Listening Session.

    This is the second of two listening sessions and takes place virtually on Wednesday, Nov. 2, 6 to 8 p.m. Attendees are asked to register by Friday, Oct. 28, at bit.ly/swellsNov2. The Zoom link will be provided to all registered attendees. Community members who cannot attend the event can learn more about the project and participate in a survey to provide feedback by visiting www.yourSCVwater.com/swells.

    During this virtual event, SCV Water’s team will answer questions from attendees, as well as share key information, including:
    •    4-1-1 on the project’s impacts and benefits
    •    How SCV Water is restoring groundwater availability due to PFAS
    •    Updates from the August Community Listening Session

    “We invite community members to join us to learn more about this ambitious treatment project that will restore local water affected by PFAS substances,” said SCV Water’s Senior Engineer Orlando Moreno, P.E. “A local, reliable water supply for our customers is critical, especially during the drought.”

    When constructed, the $16 million groundwater treatment plant, which will be located on Bridgeport Lane across the street from Bridgeport Park, will remove PFAS (per- and polyfluoroalkyl substances) using ion exchange treatment at three existing wells. 

    These wells will produce up to 6,000 gallons per minute (9,678 acre-feet per year) of groundwater. That is equivalent to water used by more than 10,000 households annually.

    The project will also ensure a local, reliable water supply for our customers and reduce our reliance on costly imported water. 

    Visit the project webpage at www.yourSCVwater.com/swells, email swells@scvwa.org or call 661-705-7253 for more information. To register for the event, visit bit.ly/swellsNov2. 

    ###


    About SCV Water: 
    The Santa Clarita Valley Water Agency (SCV Water) is a full-service regional water agency located in the Santa Clarita Valley. SCV Water provides water service to approximately 78,000 business and residential customers. It was formed on January 1, 2018, when local water suppliers combined into one integrated, regional water provider. More information can be found at www.yourSCVwater.com. 

    For more information, please contact: 

    Kathie Martin 
    Communications Manager, SCV Water 
    kmartin@scvwa.org

  • 07 Oct 2022 by Metro

    I-5 NCEP Weekly Look-Ahead: October 10 – October 16, 2022 


    Prepare for weeknight intermittent lane reductions in both directions from SR-14 to Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays and Saturdays as needed.

    SR-14 to Magic Mountain Pkwy
    Weldon Canyon Bridge rebar, concrete, excavation, shoring, and falsework preparation activity. Prepare for work in the center median and along the northbound and southbound I-5 shoulders from 7am to 4pm. | More Information

    Gavin Canyon Undercrossing bridge foundation work, crossing over The Old Road. Prepare for work along the southbound outside shoulder behind k-rail between Calgrove Bl and Weldon Canyon Rd. Activities include auger drilling, setting of steel rebar, and concrete work. Construction access from The Old Road may be utilized. | More Information

    Southbound outside shoulder excavation, shoring and retaining wall work between Calgrove Bl and Weldon Canyon Overcrossing. Prepare for intermittent closures of the southbound Calgrove Bl on-and off-ramps from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. | More Information

    Rebar, form, concrete, and falsework installation work for the Butte Canyon Bridge between Pico Canyon Rd/Lyons Ave and McBean Pkwy. | More Information

    Center median retaining wall construction, paving, and concrete barrier work.  Activities include excavation, shoring, form, and concrete work planned to continue between SR-14 and Valencia Bl. | More Information

    Slope soil stabilization (soil nail installation) along outside shoulders in both directions between Weldon Canyon bridge and Gavin Canyon Undercrossing. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information

    Magic Mountain Pkwy to Parker Rd
    Rebar, form, excavation, and utility work in the center median for the Castaic Creek Bridge between SR-126 and Hasley Canyon Rd. | More Information 

    Center median work behind concrete barriers will continue between SR-126 and Parker Rd. Activities include excavation, asphalt removal, drainage pipe installation, placement of base, stock piling of material, and paving. | More Information

    Temporary electrical work at the northbound Newhall Ranch Rd straight on-ramp. Activities include adjustments to ramp meters, ramp lighting, and installation of temporary foundations, poles, and electrical components. | More Information

    • Prepare for nightly closures of the northbound Newhall Ranch Rd off-ramp Tuesday, October 11 to Thursday, October 13 from 9pm to 5am.  
    • Northbound straight on-ramp detour:  
      • Exit I-5 to westbound Magic Mountain Pkwy, right on The Old Road, left on Henry Mayo Dr, enter northbound SR-126/Newhall Ranch Rd 
    • Exit northbound I-5 at Hasley Canyon Rd, reenter southbound I-5 at Hasley Canyon Rd, continue on southbound I-5 to SR-126/Newhall Ranch Rd 
    • Prepare for nightly closures of the southbound Hasley Canyon Rd on-ramp Tuesday, October 11 and Wednesday, October 12 from 7pm-6am.  
    • Southbound on-ramp detour:  
      • Continue southbound on The Old Road to Rye Canyon Rd, enter the southbound I-5 Rye Canyon Rd on-ramp.  

    Upcoming Activity in October
    Removal of an existing overhead sign on southbound I-5 at Newhall Ranch Rd, anticipated in late-October between 10pm and 4am. Full closure of southbound I-5 is required for this activity between SR-126 and Hasley Canyon Rd. 



    Essential Details

    • Work hours: Monday through Friday and Saturday, as needed between 7am-4pm and 7pm-6am. Crews will begin to mobilize at 6am.   
    • No two consecutive ramps in the same direction will not be closed at the same time. Detours to the next on-ramp will be posted for each closure.   
    • Traffic will be maintained in each direction.    
    • All lanes will be reopened by 6am each morning.     
    • No lane closures will be implemented during morning or evening peak traffic hours.   
    • The speed limit in construction work zones is reduced to 55-miles per hour.   

    Noteworthy 
    Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.  

     


    Metro's Community Relations team has created a Frequently Asked Questions (FAQs) document that is now available to you as a resource. |  More Information

    Our project team invites you to join our e-mailing list to get the latest details on upcoming construction. |  More Information

    See all active construction notices for this project.| More Information

     