Weekly Look-Ahead: April 29 to May 5, 2024

Weekly Look-Ahead: April 29 to May 5, 2024
29 Apr 2024 by Metro

8th Annual Older Adult Transportation Expo 
Join us at the Pasadena Convention Center on Tuesday, May 7 from 9 am to 2:30 pm for a day filled with information, resources, and fun activities all focused on helping older adults with their transportation needs. Whether you're looking for tips on using public transportation, exploring alternative transportation options, or simply want to connect with others in your community, this event is perfect for you. Don't miss out on this great opportunity to learn and engage with experts in the field. RSVP today

Weekly Look-Ahead: April 29 to May 5, 2024

Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed.

SR-14 to Magic Mountain Pkwy

Weldon Canyon Rd Bridge shoring activity. | Full Notice
Gavin Canyon Undercrossing Bridge construction. Prepare for intermittent lane reductions and closures in both directions on The Old Rd between Weldon Canyon Rd and Calgrove Bl, Monday through Friday from 9pm to 5am. View full notice for detour routes. | Full Notice
Calgrove Bl Undercrossing Bridge construction. Prepare for intermittent lane closures of Calgrove Bl between The Old Rd and Wiley Canyon Rd, Monday through Friday from 9pm to 6am. View full notice for detour routes. | Full Notice
Electrical systems work. Prepare for nightly closures of northbound McBean Pkwy on-ramp and southbound McBean Pkwy from 7pm to 6am. View full notice for detour routes. Full Notice
Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Rd and Calgrove Bl. View full notice for schedule and detour routes. | Full Notice
Center median retaining wall construction and concrete placement between SR-14 and Magic Mountain Pkwy. | Full Notice
Magic Mountain Pkwy Bridge shoring, striping, and signage and k-rail placement. | Full Notice

Magic Mountain Pkwy to Parker Rd

Castaic Creek Bridge construction. View full notice for schedule and detour routes. Full Notice
Center median concrete placement between Magic Mountain Pkwy and Parker Rd. | Full Notice

Essential Details

  • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
  • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
  • Traffic will be maintained in each direction.
  • All lanes will reopen by 6am each morning.
  • No lane closures will be implemented during morning or evening peak traffic hours.
  • The speed limit in construction work zones is reduced to 55 miles per hour.

Noteworthy

Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.