NOTE: Freeway closures are paused from Friday, September 1 to Monday, September 4 for Labor Day
Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed.
SR-14 to Magic Mountain Pkwy
Gavin Canyon Undercrossing bridge falsework grading and pile driving activity between Weldon Canyon Rd and Calgrove Bl. Traffic switch on The Old Road is moving southbound as of Thursday, August 31. Proceed with caution and watch for vehicles parked on outside shoulder near Crescent Valley Mobile Home Park. | Full Notice
Weldon Canyon Rd bridge concrete placement. | Full Notice
Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Rd Overcrossing and Calgrove Bl. | Full Notice
Center median retaining wall construction between SR-14 and Magic Mountain Pkwy. | Full Notice
Calgrove Bl Undercrossing bridge forming, rebar installation, and concrete placement between Gavin Canyon and Pico Canyon Rd/Lyons Av. | Full Notice
Magic Mountain Pkwy to Parker Rd
Full or partial lane closures of Rye Canyon Rd between The Old Road and Avenue Stanford for forming, backfilling, rebar installation and concrete placement. View the full construction notice for the schedule and detour routes. | Full Notice
Center median excavation, backfilling, and drainage pipe installation between Rye Canyon Rd and Parker Rd.| Full Notice
Santa Clara Overhead Bridge excavation and pile driving activity between Magic Mountain Pkwy and Rye Canyon Rd. | Full Notice
Castaic Creek bridge forming, backfilling, rebar installation and concrete placement between Hasley Canyon Rd Overcrossing and Biscailuz Dr. | Full Notice
Center median concrete placement between Magic Mountain Pkwy and Parker Rd. | Full Notice
Coming Soon
The overhead sign located on the existing Weldon Canyon Rd bridge is anticipated to be removed on Wednesday, September 27, 2023. This will require a full closure of the southbound side of the freeway from SR-14 to Calgrove Bl from 10pm to 4am. View the full construction notice for the schedule and detour routes. | Full Notice
Important Note
Due to pile driving activity, smoke will be visible from the I-5 freeway and The Old Rd at the Gavin Canyon Rd Bridge work zone, located between Weldon Canyon Rd and Calgrove Bl. Pile driving at this location is anticipated to continue through Summer 2023. If you have any questions regarding the active construction smoke, please call or email the I-5 NCEP hotline.
Essential Details
- Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
- No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
- Traffic will be maintained in each direction.
- All lanes will reopen by 6am each morning.
- No lane closures will be implemented during morning or evening peak traffic hours.
- The speed limit in construction work zones is reduced to 55 miles per hour.
Noteworthy
Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.