Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed.
SR-14 to Magic Mountain Pkwy
Weldon Canyon Rd bridge temporary striping and electrical systems work. | Full Notice
Gavin Canyon Undercrossing bridge falsework installation and grading, and drainage system work between Weldon Canyon Rd and Calgrove Bl. | Full Notice
Calgrove Bl Undercrossing forming of abutments, rebar installation, concrete placement, and electrical system work between Gavin Canyon Undercrossing and Pico Canyon Rd/Lyons Av. Prepare for intermittent full lane closures of Calgrove Bl, between The Old Rd and Wiley Canyon Rd, anticipated on Tuesday, October 17 from 9pm to 6am. View full notice for detour routes. | Full Notice
Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Rd and Calgrove Bl. View full notice for schedule and detour routes. | Full Notice
Center median retaining wall construction and drainage system work between SR-14 and Magic Mountain Pkwy. | Full Notice
Magic Mountain Pkwy to Parker Rd
Full closures of Magic Mountain Pkwy between The Old Rd and Tourney Rd for bridge construction, anticipated on Wednesday, October 18 from 9pm to 5am. View full notice for schedule and detour routes. | Full Notice
Full or partial lane closures of Rye Canyon Rd between The Old Rd and Avenue Stanford for backfilling. View full notice for schedule and detour routes. | Full Notice
Santa Clara Overhead Bridge forming of abutments, rebar installation, concrete placement, excavation, and pile driving activity between Magic Mountain Pkwy and Rye Canyon Rd. | Full Notice
Center median retaining wall construction, concrete placement, and drainage system work between Hasley Canyon Rd and Parker Rd. | Full Notice
Coming Soon
Demolition of the existing Weldon Canyon Rd Bridge, requiring a 12-hour full closure of the northbound and southbound I-5 between SR-14 and Calgrove Bl, anticipated on Saturday, November 4, 2023 from 8pm to 8am. | Full Notice
Essential Details
- Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
- No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
- Traffic will be maintained in each direction.
- All lanes will reopen by 6am each morning.
- No lane closures will be implemented during morning or evening peak traffic hours.
- The speed limit in construction work zones is reduced to 55 miles per hour.
Noteworthy
Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.
|
|