I-5 NCEP Weekly Look-Ahead June 5 to June 11, 2023
Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed.
SR-14 to Magic Mountain Pkwy
- Weldon Canyon Rd bridge construction. One-way traffic control with a flagger will be used as needed at Weldon Canyon Rd/Coltrane Av. | Full Notice
- Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Overcrossing and Magic Mountain Pkwy. | Full Notice
- Center median retaining wall construction between SR-14 and Magic Mountain Pkwy. | Full Notice
- Gavin Canyon Undercrossing bridge foundation work along the northbound shoulder, between Calgrove Bl and Weldon Canyon Rd. | Full Notice
- Butte Canyon bridge falsework removal in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | Full Notice
Magic Mountain Pkwy to Parker Rd
- Full closures of Rye Canyon Rd between The Old Road and Avenue Stanford. View the full construction notice for schedule and detour routes. | Full Notice
- Electrical work in the center median and northbound and southbound on-ramps at Newhall Ranch Rd. | Full Notice
- Center median work between Magic Mountain Pkwy and SR-126. | Full Notice
- Concrete placement in the center median between Magic Mountain Pkwy and Parker Rd. | Full Notice
Essential Details
- Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
- No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
- Traffic will be maintained in each direction.
- All lanes will reopen by 6am each morning.
- No lane closures will be implemented during morning or evening peak traffic hours.
- The speed limit in construction work zones is reduced to 55 miles per hour.
Noteworthy
Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.
|
- Metro's Community Relations team has created a Frequently Asked Questions (FAQs) document that is now available to you as a resource. | More Information
- Our project team invites you to join our e-mailing list to get the latest details on upcoming construction. | More Information
- See all active construction notices for this project.| More Information
|
|
|
Let's Ride Safely Together: Keeping riders safe is our number one priority and we're committed to providing you with a great experience on Metro. That's why we've launched a plan that reimagines the way we approach public safety, to ensure all our riders feel safe, comfortable, and welcome on our system. Check out 'Let's Ride Safely Together' to learn how we're improving security, cleanliness, and customer care on our buses and trains.
|
|
|
|
|