I-5 NCEP Weekly Look-Ahead: July 14 to July 30, 2023

I-5 NCEP Weekly Look-Ahead: July 14 to July 30, 2023
21 Jul 2023 by Metro

Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

SR-14 to Magic Mountain Pkwy 

Weldon Canyon Rd bridge construction. One-way traffic control with a flagger will be used as needed at Weldon Canyon Rd and Coltrane Av. | Full Notice  

Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Rd Overcrossing and Pico Canyon Rd/Lyons Av. | Full Notice 

Center median retaining wall and drainage system construction between SR-14 and Magic Mountain Pkwy. | Full Notice 

Gavin Canyon Undercrossing bridge drilling activity between Weldon Canyon Rd and Calgrove Bl. | Full Notice 

Butte Canyon bridge forming and steel rebar installation in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | Full Notice 

Calgrove Bl Undercrossing bridge forming, rebar installation and striping between Gavin Canyon and Pico Canyon Rd/Lyons Av. Full Notice 

Magic Mountain Pkwy to Parker Rd  

Full or partial lane closures of Rye Canyon Rd between The Old Road and Avenue Stanford. View the full construction notice for the schedule and detour routes. | Full Notice 

Castaic Creek bridge concrete placement utilizing daytime lane closures, between SR-126 and Hasley Canyon Rd. | Full Notice  

Center median roadway base activity between Magic Mountain Pkwy and SR-126. | Full Notice  

Center median concrete placement between Magic Mountain Pkwy and Parker Rd. | Full Notice  

Important Note 

Due to pile driving activity, smoke will be visible from the I-5 freeway and The Old Rd at the Gavin Canyon Rd Bridge work zone, located between Weldon Canyon Rd and Calgrove Bl. Pile driving at this location is anticipated to continue through Summer 2023. If you have any questions regarding the active construction smoke, please call or email the I-5 NCEP hotline. 

Essential Details    

  • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
  • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.    
  • Traffic will be maintained in each direction.     
  • All lanes will reopen by 6am each morning.      
  • No lane closures will be implemented during morning or evening peak traffic hours.    
  • The speed limit in construction work zones is reduced to 55 miles per hour.    

Noteworthy    

Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.