I-5 NCEP Weekly Look-Ahead: January 8 to 14, 2024

I-5 NCEP Weekly Look-Ahead: January 8 to 14, 2024
09 Jan 2024 by Metro

 

I-5 NCEP Weekly Look-Ahead: January 8 to 14, 2024


NOTE: Lane reductions of northbound I-5 between SR-14 and Calgrove Bl are ongoing for emergency repairs. Updates will be released when lanes have been reopened to full capacity. All other freeway closures are paused from Friday, January 12 to Monday, January 15 for Martin Luther King Jr. Day.

Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

SR-14 to Magic Mountain Pkwy

Weldon Canyon Rd Bridge excavation activity. | Full Notice

Gavin Canyon Undercrossing bridge falsework activity. Prepare for intermittent lane closures and lane reductions in both directions on The Old Rd between Weldon Canyon Rd and Calgrove Bl, Monday through Friday from 9pm to 5am. View full notice for detour routes. | Full Notice  

Calgrove Bl Undercrossing bridge forming, striping activity, and concrete placement. Prepare for intermittent lane closures of Calgrove Bl between The Old Rd and Wiley Canyon Rd, Monday through Friday from 9pm to 6am. View full notice for detour routes. | Full Notice

Butte Canyon bridge forming and grading activity in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | Full Notice

Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Rd and Calgrove Bl. View full notice for schedule and detour routes. | Full Notice

Center median retaining wall construction, concrete placement, and drainage system installation between SR-14 and Magic Mountain Pkwy. | Full Notice

SR-14 to Magic Mountain Pkwy

Santa Clara Overhead bridge column striping between Magic Mountain Pkwy and Rye Canyon Rd. | Full Notice

Castaic Creek bridge oncrete placement between Biscailuz Dr and Hasley Canyon Rd. | Full Notice

Essential Details

  • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
  • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
  • Traffic will be maintained in each direction.
  • All lanes will reopen by 6am each morning.
  • No lane closures will be implemented during morning or evening peak traffic hours.
  • The speed limit in construction work zones is reduced to 55 miles per hour.

Noteworthy

Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.