I-5 NCEP Weekly Look-Ahead: December 18 to 24, 2023
Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed.
SR-14 to Magic Mountain Pkwy
Weldon Canyon Rd Bridge shoring support installation. | Full Notice
Gavin Canyon Undercrossing bridge falsework activity. Prepare for intermittent full lane closures and lane reductions in both directions on The Old Rd between Weldon Canyon Rd and Calgrove Bl, Monday through Friday from 9pm to 5am. View full notice for detour routes. | Full Notice
Calgrove Bl Undercrossing bridge stem forming, concrete placement, and striping activity. Prepare for intermittent full lane closures of Calgrove Bl between The Old Rd and Wiley Canyon Rd, Monday through Friday from 9pm to 6am. View full notice for detour routes. | Full Notice
Butte Canyon bridge grading activity in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | Full Notice
Outside shoulder excavation, shoring, pipe installation, and retaining wall work in both northbound and southbound directions between Weldon Canyon Rd and Calgrove Bl. View full notice for schedule and detour routes. | Full Notice
Center median retaining wall construction, concrete placement, and pipe installation between SR-14 and Magic Mountain Pkwy. | Full Notice
SR-14 to Magic Mountain Pkwy
Santa Clara Overhead bridge forming, rebar installation, concrete placement, backfilling, and striping activity between Magic Mountain Pkwy and Rye Canyon Rd. | Full Notice
Castaic Creek bridge forming and concrete placement between Biscailuz Dr and Hasley Canyon Rd. | Full Notice
Essential Details
- Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
- No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
- Traffic will be maintained in each direction.
- All lanes will reopen by 6am each morning.
- No lane closures will be implemented during morning or evening peak traffic hours.
- The speed limit in construction work zones is reduced to 55 miles per hour.
Noteworthy
Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.
|